Commuters waiting for shorter gaps between trains on the Ahmedabad-Gandhinagar corridor will have to wait longer. Gujarat Metro Rail Corporation (GMRC) has confirmed that only two of the ten new train sets ordered for Ahmedabad Metro Phase 2 have reached the Ahmedabad depot so far, more than three years after the contract was signed.
The two trains are now going through testing and commissioning. GMRC told DeshGujarat, in a report published on November 25, that they will carry passengers only after all tests are complete and statutory safety approvals are in hand. A third set is expected soon, and the remaining seven will arrive in phases. No firm date has been given for the full fleet.
What was ordered, and when
The order went to Titagarh Rail Systems Limited, earlier known as Titagarh Wagons, in August 2023. The Letter of Acceptance was issued on August 29, 2023. Here is what the contract covers:
- 30 standard-gauge coaches, making up 10 three-coach train sets
- Value: about Rs 350 crore
- Scope: design, manufacture, supply, testing, commissioning and staff training
- Original timeline: a prototype within 70 weeks of the LOA and all sets within 94 weeks, which pointed to roughly June 2025 for full delivery
The new trains are meant to carry automated control systems, real-time monitoring, CCTV, integrated fire detection and more energy-efficient running gear.
A deadline that kept moving
The slippage has been visible for a while. Chief Minister Bhupendra Patel unveiled the first train set at Titagarh’s plant near Kolkata on December 20, 2025. At the time, PTI reported that the first train would be delivered within days and the other nine over the next five to six months.
By March 2026, GMRC was saying deliveries were expected to begin from June 2026. Now, at the end of November, the depot has two sets. In plain terms, the project is about 17 months past the original contractual target, and the bulk of the order is still to come.
Why Ahmedabad Metro Phase 2 needs these trains
Phase 2 is a 28.2 km extension that links Motera Stadium with Mahatma Mandir in Gandhinagar, with a branch towards GIFT City. Its estimated cost is Rs 5,384 crore. Parts of it have been running since 2024, but with trains drawn from the existing pool.
Across the operational network of about 68.2 km, roughly 32 train sets are in service. That fleet was sized largely for Phase 1. Stretching it over a longer network means fewer trains per kilometre, and that shows up as longer waits on the platform, especially on the Gandhinagar end where office and Secretariat traffic peaks in the morning and evening.
Demand is not the problem. In December 2025, PTI quoted a daily ridership of more than 1.6 lakh, with growth of 30 to 40 percent a year. Ten more trains would let GMRC tighten frequency without pulling sets off the older lines.
What commuters should expect
- No immediate change: the two delivered trains cannot enter service until testing and approvals finish. GMRC has not said how long that will take.
- Gradual improvement: as each set clears tests, frequency on the Gandhinagar side should improve step by step, not all at once.
- Plan for gaps: regular riders between Motera, the Gandhinagar sectors and GIFT City should keep checking GMRC timetables, since current headways are set by the existing fleet.
The delay also matters beyond Ahmedabad. Gujarat has a separate order for 24 train sets for the under-construction Surat Metro, and the state’s wider push on urban transport, from metro lines to projects like the Vadodara Ring Road, depends on suppliers meeting their dates.
For now, the honest answer to “when will trains come more often?” is: once the remaining eight sets arrive and clear safety checks. GMRC has promised phased deliveries but has not put a calendar on them.
Reporting based on DeshGujarat, DeshGujarat (March 2026), PTI via Devdiscourse and The Metro Rail Guy.